First of 500km of array cables being laid at Hornsea 3 Offshore Wind Farm site

Vessel showing cable 884 - Photo credit: Flying Focus
Vessel showing cable 884 - Photo credit: Flying Focus

Installation of the first of more than 500km of array cables is now underway at the Hornsea 3 Offshore Wind Farm site. 


From beginning to end
, the cables would stretch farther than the distance between London and Paris.

Array cables are underwater power lines that will link the project’s 197 offshore wind turbines to Hornsea 3’s two offshore converter stations so that they can transport power back to shore. They are buried up to 70m below sea level at the site in the southern North Sea. These are an essential part of Hornsea 3, an £8.5 billion infrastructure project that will generate 2.9 GW of renewable energy – enough to power more than 3.3 million UK homes.


The installation
marks the culmination of five years of work for Ørsted’s Hornsea 3 array cable team. Works have been going on throughout that time, including the manufacture of the array cables by suppliers Hellenic and Prysmian, mapping the seabed and the clearance of more than 2,300 boulders from the cable route.


C
arried out by Seaway7, the array cable installation is a key milestone on Hornsea 3 as these will transport power generated by the wind turbines to the offshore converter stations before it is then taken back to shore. 


Hornsea 3 is Ørsted’s first
European HVDC project. Its turbines generate electricity as alternating current (AC) which loses more power when transmitted over long distances, particularly underwater. To tackle this, power is converted at the offshore converter stations into direct current (DC) and then sent to shore via underwater export cables.


Luke Bridgman, Managing
Director, Hornsea 3 at Ørsted, said: 

“After almost five years of hard work we’ve reached the key moment for our array cables. The installation programme is a significant milestone that underpins the construction of Hornsea 3 Offshore Wind Farm. 


“Seeing everything come together is what
the whole team, both those at Ørsted and our suppliers, have been looking forward to. They have shown true grit and perseverance to ensure that we have successfully arrived at this point.”


Once installed, the cables are connected, tested to confirm they are working safely and correctly, and prepared for energisation
, with the whole process taking just over a year.